Rep. Will Stapp, a Fairbanks Republican on the House Finance Committee, said Friday the immense damage to oil facilities and disruption to shipping in the Middle East means oil prices aren’t likely to return to normal immediately after the war. “If the war ends tomorrow I’m pretty sure they can’t rebuild a refinery in a day,” he said.
Revised revenue forecast: $91/barrel oil, $545M extra for state for rest of fiscal year due to Iran war
Mark Sabbattini, Juneau Independent, March 13, 2026
New current-year oil price forecast of $75.26 far exceeds December’s $65.48 prediction; outlook for fiscal year starting July 1 is $75 a barrel, up from $62 in December
An average oil price of $91.09 per barrel between now and June 30 is expected to result in $545 million of extra revenue for Alaska’s state government, according to a forecast released Friday by the state Department of Revenue.
The forecast assumes a major increase in oil prices due to the two-week-old war against Iran will continue for months, but won’t extend throughout the coming fiscal year that begins July 1. Next year’s prices are expected to average $75 a barrel, “which assumes that prices will begin FY 2027 over $80.00 per barrel and decline throughout the fiscal year.”
“As always, it is important to note this forecast represents one scenario within a range of potential outcomes,” Janelle Earls, the revenue department’s acting commissioner, wrote in a cover letter for the forecast. “This is true now more than ever given current world events.”
State legislative leaders, in their initial assessments of the revised forecast, said a foremost priority is asking about the specific parameters resulting in the rosier outlook during hearings with revenue department officials early next week.
“What we’re told at this preliminary stage is they changed their sensitivity tables,” said Rep. Andy Josephson, an Anchorage Democrat who co-chairs the House Finance Committee. “And so we’re going to want to look at that, educate ourselves on that, and be ready for questions on Monday with (the Office of Management and Budget) and the Department of Revenue.”
Interest in the Alaska LNG export project has spiked since the war in the Middle East choked 20% of global LNG supply and sent Asian buyers scrambling for expensive spot cargoes.
Middle East War Revives Interest in Alaska LNG
Tsvetana Paraskova, OilPrice.Com, March 16, 2026
Glenfarne Group, the majority owner and developer of the Alaska LNG Project, aims to sign soon binding offtake agreements with buyers and advance final investment decisions to later in 2026 and early 2027, company executives told Reuters on the sidelines of an energy conference in Tokyo on Monday.
“There’s a real interest, particularly with everything happening in the Middle East right now. Everyone would like to get those (preliminary deals) turned into long-term agreements,” Adam Prestidge, president of Glenfarne Alaska LNG, told Reuters.
The $44-billion Alaska LNG project, strongly promoted and supported by the Trump Administration over the past year, has received a shot in the arm from the conflict as buyers seek greater diversification, following initial lukewarm reception of the Alaska project among Asian LNG buyers and investors.
Alaska LNG is designed to deliver North Slope natural gas to Alaskans and export LNG to U.S. allies across the Pacific. An 800-mile pipeline is planned to transport the gas from the production centers in the North Slope to south-central Alaska for exports. In addition, multiple gas interconnection points will ensure meeting in-state gas demand.
Glenfarne now looks to take the FID for the pipeline in 2026, later than a previous target in late 2025, Prestidge told Reuters. The developer also aims for an FID on the export terminal in early 2027, the executive added.
The company is now working to finalize binding agreements and ensure financing, and all these steps “are all well underway,” Prestidge said.
Last month, just before the Middle East war erupted, Glenfarne signed a preliminary 20-year agreement with TotalEnergies, under which the French supermajor, a key global LNG trader, would buy 2 million tons per year of LNG from the Alaska LNG project.
Management noted that about 95% of major mining and processing equipment items had now been received at Nova’s freight staging yard and logistics centre in the town of Willow.
Nova takes key step towards US antimony production as equipment arrives at Estelle
The Australian, March 16, 2026
- Nova Minerals receives first batch of mining and processing equipment at Estelle in Alaska
- The company plans to begin antimony mining later this year or in early 2027
- Haulage is being aided by favourable winter conditions for snow road and ice bridge construction
The company plans to produce antimony from outcropping stibnite veins at the project, with processing set to take place about 100km away at a facility in Port Mackenzie.
First production is targeted for late 2026 or early next year.
The delivery of equipment follows a US$43.4 million grant awarded by the US Government last October to help fast-track Estelle towards mining.
Subsequently, Nova Minerals (ASX:NVA) swiftly assembled an engineering, procurement and construction management team to accelerate development work.
The team was tasked with sourcing heavy equipment from across the US for trail construction and airstrip expansion, as well as extraction and processing of stibnite-bearing ore.
As a result, the mobilisation of heavy equipment is marching ahead.
Management noted that about 95% of major mining and processing equipment items had now been received at Nova’s freight staging yard and logistics centre in the town of Willow.
In addition, around 70% of the equipment has already left the facility for Estelle.
Cold winter temperatures as low as -26C are helping transport efforts, including haulage across ice bridges and along 150km of Nova’s snow road.
“Freight hauling is well underway, and with the first loads received, we have an exciting couple of weeks ahead as we prioritise the remaining critical transports before the winter freight window closes,” explained Nova Minerals general manager Hans Hoffman.
“Having this fleet of ore processing and earthworks equipment – articulated haul trucks, excavators, dozers, crushers, ore sorter, and more – in camp will be transformative.
“It will enable us to upgrade our existing infrastructure, expand the Whiskey Bravo airstrip, advance ore extraction at the antimony prospects, and establish new facilities to accelerate development across the Estelle gold and critical minerals project.”